September 18, 1997
SES 97-276
Mr. Robert Nicholls
Quality Assurance Manager
GE Nuclear Energy
175 Curtner Avenue
San Jose, CA 95125-1088
Dear Mr. Nicholls
Enclosed is a copy of Audit G-97-120 which documents the results of the Audit conducted at the San Jose, CA facility on August 18 through 22, 1997. The Audit resulted in identifying nine Findings and three Unresolved Items to GE Nuclear Energy (GENE) in which one deficiency was identified as a Level I Finding, seven deficiencies as Level II Findings, and one deficiency as a Level III Finding. In addition, this audit resulted in the identification of one Level II finding to the ComEd BWR Site Engineering Departments and Nuclear Fuel Services (NFS) Department.
The Level I finding encompasses the other eight deficiencies and reflects an overall assessment that GE Nuclear Services is ineffectively implementing its Quality Assurance Program in the design area. Due to the extensive nature and severity levels of the subject audit findings, ComEd Supplier Evaluation Services (SES) issued a Stop Work to GENE Nuclear Services for the safety related engineering and design activities performed at San Jose, CA for all ComEd BWR Stations (Dresden, Quad Cities, and LaSalle County) on August 29, 1997.
GENE will be required to provide a written response to the Findings and the Unresolved Items by October 10, 1997. (CAR Nos. G 97-120-01 through 08 and CAR Nos. G-97-120-10 through 13). The subject CARs were transmitted to the GENE QA Manager on September 8, 1997 for the purpose of an expedited corrective action.
The cooperation and assistance extended to the Audit Team by GENE personnel during the Audit was greatly appreciated.
September 18, 1997
SES 97-276
Mr. Robert Nicholls
Page 2
If you have any questions please contact Oscar Shirani, ComEd Supplier Evaluation Services (SES), at Tel.No. 630-663-7934.
Sincerely,
Oscar B. Shirani, PE
Audit Team Leader
OS:jkw/g:\qv\97audits\G-97-120.rpt
cc: J. Hosmer
L. Waldinger
S. Perry- Dresden
W. Subalusky - LaSalle
E. Kraft
D. Winchester - Dresden
J. McDonald - LaSalle
F. Famulari - Quad Cities
G. Poletto - LaSalle
R. Renuart
R. Freeman - Dresden
J. Hutchinson - Quad Cities
W. Pearce - Quad Cities
T. Rieck
E. Netzel
Audit File G-97-120
Duplicate File
Memorandum
Date: September 18, 1997
SES-97-276
To: Mr. J. Hosmer
Engineering Vice President
From: Oscar Shirani
Subject: ComEd Audit of GENE - G-97-120
Enclosed is a copy of Audit G-97-120 which documents the results of the Audit conducted at the San Jose, CA facility on August 18 through 22, 1997. The Audit resulted in identifying nine Findings and three Unresolved Items to GE Nuclear Energy (GENE) in which one deficiency was identified as a Level I Finding, seven deficiencies as Level II Findings, and one deficiency as a Level III Finding. In addition, this audit resulted in the identification of one Level II finding to the ComEd BWR Site Engineering Departments and Nuclear Fuel Services (NFS) Department.
The deficiency issued to ComEd Engineering was for the failure to utilize the Nuclear Design Information Transmittal (NDIT) process to transfer design information to GENE.
Due to extensive nature and severity levels of the subject audit findings, ComEd Supplier Evaluation Services (SES) issued a Stop Work to GENE Nuclear Services for the safety related Architect/Engineering and design activities performed at San Jose, CA for all ComEd BWR Stations (Dresden, Quad Cities, and LaSalle County) on August 29, 1997.
ComEd BWR Site Engineering Departments and the Nuclear Fuel Services (NFS) Department will be required to provide a written response to the Finding CAR No. G-97-120-09 by October 10, 1997. The subject CAR was transmitted to ComEd’s Engineering Vice President on September 8, 1997 for the purpose of an expedited corrective action.
September 18, 1997
SES-97-276
Mr. J. Hosmer
Engineering Vice President
Page 3
If you have any questions please contact Oscar Shirani, Supplier Evaluation Services (SES), at ext. 8-347-7934 Downers Grove.
cc: L. Waldinger
S. Perry- Dresden
W. Subalusky- LaSalle
E. Kraft- Quad Cities
D. Winchester- Dresden
J. McDonald- LaSalle
F. Famulari- Quad Cities
G. Poetto- LaSalle
R. Renuart
R. Freeman- Dresden
J. Hutchinson- Quad Cities
W. Pearce - Quad Cities
T. Rieck
E. Netzel
Audit File G 97-120
Duplicate File
ComEd
A Unicom Company
Audit Report
for
Special Audit G-97-120
GE Nuclear Energy
175 Curtner Avenue
San Jose, CA 95125-1088
Prepared By: __________________________________ Date:__________________
Oscar B. Shirani, PE
Audit Team Leader
Approved By: __________________________________ Date:__________________
Edward R. Netzel, PE
Supplier Evaluation Services Director
Vendor Name / Address
GE Nuclear Energy
175 Curtner Avenue
San Jose, CA 95125-1088
Audit Dates
August 18-22, 1997
Audit Purpose and Scope
GE Nuclear Energy (GENE) was contracted by ComEd to perform various safety related Architect/Engineering activities. The focus of this Audit was to review the implementation of their quality program for providing engineering services to ComEd.
The focus of this audit was to validate potential similar technical and design control issues that were identified during the Dresden ISI for the engineering activities that GENE is providing to ComEd.
The primary scope of the audit was the design control requirements of 10CFR 50 Appendix B as they apply to engineering services and specifically safety related calculations. This was a performance based audit which reviewed the activities and documentation of GENE QA program in the areas of order entry, design control, design interfaces, software control, technical adequacy of design documents, corrective action identification and internal audits in the design area.
Implementation of all the general Quality Assurance program elements, such as procurement, material control, fabrication, calibration, test/inspection, document control, organization, nonconforming items/part 21, external audits and records was not reviewed during this audit.
Quality Programs
The following GENE Quality Assurance Programs was in place at the time of this Audit:
GE Nuclear Energy Quality Assurance Program Description NEDO-11209-04A Revision 8, March 31, 1989
References
10CFR50 Appendix B - Criterion II, III, XVI, and XVIII
ANSI N45.2
GE Nuclear Energy Quality Assurance Program Description NEDO-11209-04A Revision 8, March 31, 1989 and various Engineering Operating Procedures
Checklist
An augmented NUPIC Revision 7 checklist was utilized during the performance of the Audit.
Program Effectiveness Statement
GENE has established a QA Program based upon the requirements of ANSI N45.2, NRC Regulatory guide 1.28, and 10CFR50 Appendix B. This audit was focused on the design control process with emphasis on a rigorous technical review of calculations. The audit also evaluated the GE/ComEd interface with regard to the transfer of design information.
The audit examined fifteen (15) General Electric Nuclear Services Design Record Files (DRF’s). The audit team performed a rigorous technical review of fifty four (54) calculations contained within the fifteen (15) G.E. DRF’s. There were nine findings and three unresolved items identified against GE in the audit. These results revealed a general lack of formality in the documentation supporting the design review process. Also technical questions regarding assumptions, references, design inputs, software verification/validation and insufficient detailed analysis were raised during the audit. Due to the quantity and nature of issues identified, the independent design review process was deemed ineffective. Furthermore, the QA independent oversight was found to be ineffective at reviewing the design portion of the DRF’s. Consequently ComEd Supplier Evaluation Services (SES) issued a finding to GENE Nuclear Services for not effectively implementing its QA Program in the area of design. Also ComEd SES issued a stop work order on August 29, 1997, to GENE Nuclear Services for safety related Engineering and Design activities performed for ComEd BWR stations.
In order to facilitate an expedited corrective action review, the ComEd Corrective Action Records (CAR’s) were transmitted to GENE on September 8, 1997. ComEd Problem Identification Forms (PIF’s) were issued to address the technical issues raised from the audit. The ComEd BWR site engineering organizations, ComEd Nuclear Fuel Services (NFS), and ComEd Nuclear Engineering Services (NES) reviewed the issues with GE for potential operability. No operability issues were identified.
Specific details regarding the evaluations performed during the audit and the types of deficiencies identified for each calculation can be found in the Audit Summary Section of this report. More detail regarding all of the deficiencies can be found in the Audit Findings Section of this report and in the attached Corrective Action Records (CAR’s).
ComEd Definition & Classification of Finding and Unresolved Item
Definition
Finding - a condition affecting the safety and/or reliability of the unit(s) or an identified noncompliance with regulations which requires corrective action.
Classification
Level I - a condition which does affect the safety and/or reliability of the unit(s) or a significant breakdown in the QA Program.
Level II - a condition which may affect the safety and/or reliability of the unit(s) or a major noncompliance in the QA Program.
Level III - a condition that probably does not affect the safety and/or reliability of the unit(s) but is a substantive deviation from implementing procedures.
Unresolved Item: A condition that is not a finding, may be an opportunity for improvement; or if left unaddressed, could potentially result in an unacceptable condition. This item may require an evaluation and response by the auditee or may require further audit investigations to determine its status.
Audit Findings:
One Level I, Seven Level II, one Level III Findings and three Unresolved Items were issued to GENE, and one Level II was issued to ComEd Engineering as a result of this audit.
Finding Level II (CAR G 97-120-01)
Numerous administrative and editorial errors were found in GENE design documents. Examples of these errors include document legibility, page numbering, record identification, changes made improperly and suitable identification of the preparer & reviewer. These discrepancies reveal a lack of formal control in the GENE design control process.
Finding Level II (CAR G 97-120-02)
Due to the numerous design control deficiencies being identified during this audit, the GENE independent design review process was determined to be ineffective.
Finding Level II (CAR G 97-120-03)
Numerous GENE calculations were found to have design control deficiencies such as unjustified assumptions, references lacking, design input errors, and inadequate detailed analysis.
Finding Level III (CAR G 97-120-04)
Design Record Files (DRFs) had missing contractual agreements as required per GENE procedures.
Finding Level II (CAR G 97-120-05)
ComEd Engineers performed and reviewed design analysis calculations under GENE QA Program without being employed and indoctrinated to GENE procedures.
Finding Level II (CAR G 97-120-06)
GENE's internal audits are ineffective in independently overviewing the design analysis area.
Finding Level II (CAR G 97-120-07)
Computer software frequently used at GENE lacked evidence of being verified and validated.
Finding Level II (CAR G 97-120-08)
GENE was provided design input data by Sargent & Lundy for ComEd projects without a formal design interface
Finding Level II (CAR G 97-120-09)
ComEd Engineering failed to use the Nuclear Design Information Transmittal (NDIT) process to transfer information to GENE. Letters or facsimiles were utilized to transmit design input documents to GENE calculations.
Unresolved Item (CAR G 97-120-10)
GENE NEDE-31744, Procedure No. 10-27 needs to reference 10CFR50 Appendix B since its scope includes safety related work.
Unresolved Item (CAR G 97-120-11)
Documentation for computer programs were unavailable for review during the audit.
Unresolved Item (CAR G 97-120-12)
The cognizant engineer was unavailable to answer questions regarding specific design documents.
Finding Level I (CAR G 97-120-13)
GENE has not effectively implemented its Quality Assurance Program in the area of design.
AUDIT SUMMARY
Introduction
ComEd has contracted with GENE to perform safety related Architect/Engineering services.
Order Entry/Specifications:
A review of the GENE incoming orders revealed that the incoming orders are processed into the GENE system through the use of Engineering Operating Procedures EOP-25-2.00 rev. 3, EOP 42-10.00 rev. 7, and GENE Policies & Procedures (P&P) NEDE-31746 Procedure No. 10-27 issued 9/94.
Procedure 10-27 requires that the responsible business manager ensures that a completed, reviewed and approved proposal authorization and/or proposal change authorization as appropriate is in place to support a proposal prior to issuance. The proposal shall adequately describe the product/service and delivery schedule requirements specified by the customer. Before entering into any contract, the QA Manager shall assess the GENE ability to comply with applicable QA Program requirements of NEDO-11209-04A, revision 8. Evidence of the purchase order acceptance reveals the translation of the customer’s purchase order, utility/plant, conversion of marketing record on ISIS number, approvals from appropriate level of management, and other related information.
The ComEd purchase orders address the GENE’s proposal correspondences. The Design Record File (DRF) is intended to be the formal controlled information record for in-process and completed engineering work which is retained and from which information can be retrieved. EOP 42-10.00 Appendix D, rev. 7 indicates that all DRFs require an assignment sheet, a table of contents, and any supporting information required by EOPs. Supporting information includes contractual or commercial documents which supply customer unique requirements (e.g., QA and design inputs). Contrary to the procedural requirements, many GENE DRFs did not include the ComEd purchase orders. This area was found deficient and identified as a Level III Finding CAR-G-97-120-04.
In addition, the scope of the Policy & Procedure NEDE-31744, Procedure NO. 10-27, issued 9/94 "Proposal & Sales Contract" references ISO-9001 and has also been utilized for safety related contracts. There is no reference to 10CFR50 Appendix B. Unresolved Item G-97-120-10 was issued to revise the subject procedure and incorporate a reference to 10CFR 50 Appendix B.
Design and Software
This audit reviewed the translation of design input documentation and the subsequent use of the design inputs, assumptions, methodology, references, summaries and conclusions into the GENE program for the development of engineering calculations. A rigorous technical review was performed on a population of 54 design calculations in 15 DRFs from the identified population of 42 DRFs containing safety related design calculations. Since there were only two electrical I&C DRFs the audit team excluded them from the population of the selected DRFs. The 54 calculations were completed by G.E. within the last three years and covered the Structural, Mechanical, and Nuclear Engineering disciplines. The calculations were a composite of design basis, plant operability, and supporting plant modifications and were based upon PRA significant systems.
There were 49 of 54 design documents selected that had a variety of administrative and editorial discrepancies including document legibility, page numbering, record identification which revealed a lack of formal control in the GENE design control process. Additionally, there were 25 of 54 design documents containing discrepancies involving the documentation of the independent design review. Additionally, there were also 45 of 54 design documents found to have design control deficiencies such as unjustified assumptions, references lacking, design input errors, and inadequate detailed analysis. No design documents were found to be free of any deficiencies. As a result of all the numerous deficiencies found in the design documents, the audit team assessed that the independent design verification process was ineffective.
The following is a summary of the technical specialists’ comments on the 54 calculations that were reviewed during this audit at GENE in San Jose, CA. See the referenced Corrective Action Records (CAR’s) for specific composite details concerning the deficiencies that were identified. The calculation summaries are provided as follows:
1. CORE SPRAY CRACK ANALYSIS FOR QUAD CITIES UNITS 1 & 2: DRF No. 137-0010-7; ISIS No. 1EXB5 (GENE-523-A80-0594, DATED 6/9/94
A. INTRODUCTION
This DRF performs evaluations of a crack indication on the "B" core spray line at the Quad Cities Unit 1. This indication was identified during an inspection in response to IE Bulletin 80-13. The crack indication is located outside the shroud, just inside the vessel, where the piping and the junction box meet in the heat affected zone of the weld. The crack is estimated to be approximately 120° of the outer circumference of the pipe. Using the top of the core spray pipe as reference of 0° azimuth, the crack was located from approximately 30° azimuth to 150° azimuth.
B. DRF CONTENT
This DRF (#137-0010-7) contains seven (7) calculations that perform various evaluations related to the subject crack as follows:
Determination of Loads: Tab B
Allowable Crack Size Tab C
Crack Growth / Leakage Tab D
Vibration Analysis Tab E
Fatigue Analysis Tab F
Thermal Mismatch Analysis Tab G
Displacement Calculation Tab N
Tab M includes the summary report based on the above seven calculations.
C. EVALUATION
C.1 GENERIC FINDINGS APPLICABLE TO ALL TABS
(CAR No. G-97-120-4)
Specific findings for applicable calculations are provided separately in the subsequent paragraphs here.
C.2 TAB B : DETERMINATION OF LOADS
In this calculation, a finite element model of the Quad Cities 1 & 2 core spray line was developed to calculate the stresses at the crack location due to dead weight and seismic loadings. ANSYS computer code was used to perform the analysis. This calculation is deficient in the following respects:
C.3 TAB C: ALLOWABLE CRACK SIZE
In this tab, the allowable through-wall crack size is calculated based on plastic hinge formation methodology given in a published reference. This methodology is acceptable, however, the reference is not fully documented and various variables used in the analysis are not defined in this calculation. More complete documentation, however, is provided later for the plastic hinge formation methodology in Tab M (CAR No. G-97-120-3).
C.4 TAB E: VIBRATION ANALYSIS
GE performed vibration analysis for Monticello core spray crack configuration considering vibration data from Kuosheng I reactor (NEDE 22146). For the Monticello analysis, justification for using the Kuosheng I data was based on the similarity of the geometry of the Monticello and Kuosheng I core spray lines and the vortex shedding frequencies of the two lines. Results found the Monticello core spray line unaffected by vibrational loading.
The present calculation, on page 2 of Tab E states that "Since Quad Cities appear at least as rigid as Monticello based on geometry and since the Monticello analysis very conservatively demonstrated that vibrational loading is not a factor, vibrational loading is not expected to affect the Quad Cities 1 & 2 core spray lines."
The above statement, in reality, is based on two levels of similarity - viz. Kuosheng I Vs Monticello and Monticello Vs Quad Cities. This makes the evaluation very approximate. A specific comparison based on the geometry, stiffness and supports of the Monticello Vs Quad Cities piping systems is not performed to justify the applicability of the Monticello vibration analysis to the Quad Cities vibration analysis.
It will result in a better evaluation if a modal analysis of the Quad Cities Piping is performed since a finite element model already exists for this system in Tab B. Based on the frequencies from the modal analysis and the vortex shedding frequency, a better evaluation for vibration can be performed for the Quad Cities crack configuration.
It may further be noted that no reference (such as report number, document number etc.) is provided in the calculation for the Monticello vibration analysis. (CAR No. G-97-120-3).
C.5 TAB F: FATIGUE ANALYSIS
Fatigue crack growth behavior of austenitic stainless steels is affected by a number of parameters such as environment, material variability, geometry, mean stress and R ratio (Kmin/Kmax). In Tab F, a Fatigue Crack Growth Analysis for the Quad Cities Units 1 & 2 core spray system is documented. This analysis is based on the effects of fatigue due to thermal shock loading on crack growth rate for Monticello core spray line crack. However, there is no documentation provided which shows that the material, environment, geometry, and R ratio parameters of the Quad Cities core spray crack are bounded by the Monticello core spray crack. Objective evidence should be provided by GE by comparing the various material and crack geometry/stress parameters to establish the applicability of the Monticello core spray crack fatigue analysis to Quad Cities core spray crack fatigue evaluation
It may further be noted that no reference (such as report number, document number etc.) is provided in the calculation for the Monticello fatigue crack growth analysis. (CAR No. G-97-120-3).
C.6 TAB G: THERMAL MISMATCH
In Tab G, on p. 1 it is stated that "Based on similar geometries of the core spray lines and similar locations of the cracks, the Monticello and Quad Cities Units 1 & 2 systems are considered comparable with regard to this analysis." No detailed basis for this consideration (such as crack parameters and orientation / location comparison between Monticello and Quad Cities cracks) are provided by GE for the thermal mismatch analysis.
It may further be noted that no reference (such as report number, document number etc.) is provided in the calculation for the Monticello thermal mismatch analysis. (CAR No. G-97-120-3).
C.7 TAB N: DISPLACEMENT CALCULATION
Tab N includes the displacement calculation for the core spray line crack. In this calculation, an evaluation is made for postulated pipe break of the Quad Cities core spray line. The ANSYS finite element model of Tab B is modified to include a pipe break at the crack location. Based on this modified model, displacements of the pipe ends are calculated. Based these displacements, a total area through which leakage occurs is calculated as 2.2 in2. Based on this area, the leakage flow is determined to be 656 gpm. This calculation is deficient due to the following:
On page 2, it is stated that "P - Pinf = 64 psid (Source: Luke Jen, Core Spray LSE)." This is an incomplete reference. GE should provide the complete reference for this information.
On page 2, it is stated that "Dr. Fred Moody has reviewed both the methodology and calculations of this analysis and has concurred with its results". However, there is no objective evidence (signature of Dr. Fred Moody) in this calculation. Note that the Q. A. form (included with summary report in Tab M), for Preparer/Reviewer/Approver’s signatures, does not contain Dr. Fred Moody’s name. There is no letter/fax signed by Dr. Moody indicating that he has actually reviewed and concurred with this analysis. Proper letter/fax reference from Dr. Moody should be included in this Tab N (CAR No. G-97-120-3).
Two pages following page 4 have no page numbers. These two pages appear to be scratch pages, informally marked during some discussion, and out of context (CAR No. G-97-120-1).
C.8 TAB M: "CORE SPRAY CRACK ANALYSIS FOR QUAD CITIES UNITS 1 & 2"
Tab M provides the summary report for the core spray crack analysis for Quad Cities Units 1 & 2.
In this report, an analysis is presented for the Quad Cities core spray piping, to determine the allowable through-wall circumferential crack for which failure by plastic collapse might occur. In particular the following equations are used to determine the limiting crack size for a circumferential crack not penetrating the compressive side of the pipe:
Pb = [2 s f / p ] [2 sin b - (d/t) sin a ]
b = [p - (a /t)d - (Pm/s f) p ] / 2
where:
Pb = piping bending stress
Pm = piping membrane stress
a = half flaw angle
d = flaw depth
t = thickness of the pipe
This methodology is acceptable per ASME Boiler & Pressure Vessel Code, Section XI, Appendix C, (p. 392, 1995 Edition).
This report (Tab M) does not provide references to applicable calculations which are used as bases for the conclusions in the report. For example, the reference to the calculation containing the ANSYS finite element analysis of the core spray line in the vicinity of the crack is not provided. In the summary report (Tab M), it is stated that to assess the potential of flow induced vibrations for the cracked core spray line, additional analyses were conducted assuming a 180° through-wall crack. However, the references for these analyses are not provided in the report. (CAR No. G-97-120-1).
2. FINAL REPORT OF THE IMPACT EVALUATION OF USING GE9 80-MIL FUEL CHANNELS FOR THE LASALLE UNITS 1 & 2 - DRF NO.: A12-00098; ISIS NO.: 1ESR5, REPORT NO.: GE-NE-523-A191-1294 (DATED 10/9/95)
A. INTRODUCTION
LaSalle Units 1 & 2 originally used 100-mil thick fuel channels for GE9 fuel. These analyses are performed by GE to evaluate impact of using 80-mil thick fuel channels for GE9 fuel in LaSalle Units 1 & 2.
The fuel channel thickness is important to the reactor pressure vessel (RPV) and internals, and the surrounding structure. The overall dynamic response of the entire reactor vessel, including shroud and internals is affected by this important change.
In this DRF, GE performed the horizontal seismic (OBE and SSE) analyses, the vertical fuel-lift analysis, and the life evaluation analysis for the 80-mil channel configuration. The horizontal mathematical models used for seismic analyses were developed using equivalent beam and spring elements to represent the stiffness of reactor pressure vessel (RPV) and major internal components. Masses of the RPV and internals were lumped at nodes connecting the beam and spring elements. The inertial effects that the RPV and internal components incur due to motion of the adjacent fluid was also simulated in the model. Multi-unit components such as fuel assemblies and the control rods were modeled as equivalent beam and spring elements. The seismic analysis was performed using GE program SAP4G07. Response spectra at specified locations were generated from the elevated time histories using GE program SPECA05C.
B. DRF CONTENT
This DRF contains two binders each 4" thick and it includes the following three analyses for the LaSalle 80-mil channels:
C. EVALUATION
A review of the analyses contained in this DRF (DRF A12-00098 - ISIS No. 1ESR5), resulted in the following findings:
C.1
Part of the input data for the analyses performed in DRF A12-00098 (ISIS No. 1ESR5), were transmitted to GE by a letter from Sargent & Lundy (Reference 7: Letter from S. Singh of S & L to P. Shah of GE dated July 26, 1994). No NDITs were used, as such the validity of the input - and consequently the output (final analysis results) - is questionable. Since the input primarily consisted of the detailed finite element model of the reactor vessel, including shroud and all internals, all analyses are affected by any potential error in the input data (CAR No. G-97-120-8).
C.2
Part of the input data for the analyses performed in DRF A12-00098 (ISIS No. 1ESR5), were transmitted to GE by a fax from ComEd -Dresden site- (Reference 6: Fax from T. Behringer of ComEd to P. Shah of GE dated 7/22/94). No NDITs were used, as such the validity of the input - and consequently the output (final analysis results) - is questionable. (CAR No. G-97-120-9).
C.3
The vertical fuel-lift analysis was performed by using an in-house computer code for non-linear analysis. This analysis is described on page 6 of the DRF, but no reference is provided for the GE non-linear in-house code used in the analysis (CAR No. G-97-120-3). GE engineer indicated that they used SEISM02 program for this analysis. Validation documentation for the SEISM02 program was not available for review. This is an Unresolved Item (CAR No. G-97-120-11).
C.4
Validation documents for SAP4G07, SPECA05C, and CHANL01V programs used in this DRF were also not available for reviews. This is an Unresolved Item (CAR No. G-97-120-11).
C.5:
In DRF A12-00098 (ISIS No. 1ESR5), changes made by hand on pages A-3, A-5, and page # 224 of computer listing in index 5 are not initialed by the preparer and the reviewer. (CAR No. G-97-120-1).
In DRF A12-00098 (ISIS No. 1ESR5), all the figures and tables have no record identification numbers. (CAR No. G-97-120-1).
In DRF A12-00098 (ISIS No. 1ESR5), all pages of computer output for SAPG07 program (about 6" thick output) have no record identification numbers (CAR No. G-97-120-1).
C.6
In this DRF (DRF A12-00098 - ISIS No. 1ESR5), no analysis is performed for the SRV and other hydrodynamic high frequency loadings for the new (80-mil) RPV finite element model. A detailed, documented comparison of the various structural frequencies should be performed in relation to the SRV spectral peaks for the new (80-mil) and old (100-mil) RPV finite element models to determine the potential impact of the combined hydrodynamic and seismic loadings. This is required to satisfy the original design basis loading criteria for the plant for the 80-mil configuration per the LaSalle UFSAR load combinations (CAR No. G-97-120-3).
C.7
In this DRF (DRF A12-00098 - ISIS No. 1ESR5), the channel lifetime evaluation is performed by GE using an in-house program CHANL01V. This program is used by GE to predict acceptability of the channel design. However, these predictions have unqualified uncertainties. The channel lifetime evaluation consists of determining the possibility of excessive channel to control rod friction, such that interference with normal control rod motion occurs. The interference depends on a number of parameters such as:
Some of the above parameters are accounted for by GE program in a simplified, statistical way. This is not acceptable, since the parameters listed above cannot be represented accurately by analytical models. As such the results by this program could vary considerably and may not represent actual operating situation. Moreover, in this approach, no account is made for the adhesive wear and localized asperity contact deformation at the interface which primarily control friction. GE should not use this analytical method for life prediction but instead develop, controlled tests based on field data and use more deterministic approach to predict life (CAR No. G-97-120-3).
3. "Structural Evaluation of Potential Top Guide & Core Plate Cracking at Dresden 2 & 3," DRF No. 137-0010-8, GE-NE-523-A081-0895, ISIS No. 1FQQX, Dated 12/1/95.
4. "Response to Commonwealth Edison Technical Audit Questions", DRF No. 137-0010-7, GE-NE-523-A69-0594, ISIS No. 1EXB8, Dated 6/20/94.
5. "KVS a Profile for H5 Weld", DRF #137-0010-7, GE-NE-523-A69-0594, ISIS No. 1EXB8, Dated 6/20/94.
6. "Evaluation of the Indications Found at H5 Weld in Dresden Unit 3", DRF No. 137-0010-7, GE-NE-A69, ISIS No. 1EXB8, Dated 6/7/94.
7. "LaSalle Unit 1 and Unit 2, Riser Pipe Flaw Evaluation Handbook", DRF No. B13-01869-009, ISIS No. 1G5WA, Dated 3/26/97.
8. "LaSalle Unit 1 and Unit 2, Riser Pipe Flaw Evaluation Handbook, Verify FIV Stress", DRF No. B13-01869-009, GE-NE-523-B13-01869-009/TAB9, ISIS No. 1G5WA, Dated 3/26/97.
9. "Dresden 2 In-Vessel Visual Inspection Flaw Acceptance/Disposition Criteria", GE DRF No. 137-0010-7, ISIS No. 1F3ST
10. "Evaluation and Screening criteria for the Dresden 3 Shroud Indication", DRF No. 137-0010-7, ISIS No. 1EJJ5, Index 2, sheet no. 2-1 to 2-34.
11. Portion of this DRF, dated 4/12/95, " RCIC System Performance Calculations for Operating Plant", DRF No. E51-00178 Volume 1, Section 6, ISIS No. LS509
12. Portion of this DRF, dated 8/15/96/, " RCIC System Performance Calculations for Operating Plant", DRF No. E51-00178 Volume 1, Section 6, ISIS No. LS509
13. DRF T23-00740, "Dresden DBA LOCA Containment Analysis 1 LPCI/ Containment Cooling Pump and 2 CCSW Pumps," Jan 97
15 calculations exist in the DRF
18 miscellaneous items exist in the DRF including letters, reports, digitizing of data, etc.
Reviewed (4) calculations and (1) report:
Section 1.0 Heat Exchanger K value (Calculation)
Section 2.1 SHEX Analysis Cases 2, 2A, 2B (Calculation)
Section 2.7 SHEX analysis with Containment Heat Sinks Cases 2A1, 2B1, 3A1, 3B1 (Calculation)
Section 2.9 SHEX Analysis (Calculation)
Section 4.4 GE-NE-T2300740-2 (Report)
14. DRF A00-00648-5, "SHEX-04V Engineering Computer Program," June 23, 1993
14 sections exist in the DRF to control this software
Reviewed all 14 sections
15. DRF A00-03049, "SAFER-04 Engineering Computer Program," May 26, 1988
15.1 DRF A00-03049-1, April 25, 1991
15.2 DRF A00-03049-2, June 18, 1993
15.3 DRF A00-03049-3, October 5, 1993
12 sections exist in the DRF A00-03049 to control this software
Reviewed 8 sections in DRF A00-03049
Reviewed 1 section of A00-03049-1
Reviewed 2 sections of A00-03049-2
Reviewed 2 sections of A00-03049-3
16. DRF B13-01760, "LaSalle SRV Removal"
At least 6 calculations exist in the DRF
Many miscellaneous items exist in the DRF including letters, reports, references, etc.
Reviewed (5) sections representing (5) calculations and the final reports:
Availability Section
ATWS Section
Section 2.4 ODYN analysis
Section 2.6 SRVOOS Impact on Thermal Fatigue
Section 3.0
GE-NE-B13-01760 Report
17. DRF 137-0010-7, Tab O, "Quad Cities Core Spray Crack"
At least 5 SAFER/GESTR-LOCA calculations exist in the DRF
Reviewed (1) sections representing (5) calculations and the final reports:
Letter with SAFER/GESTR-LOCA Evaluation Section
18. MSLB TRACG ANALYSIS-DRF L12-00817 (ISIS No. 1FA4Z, DRF L12-00819)
The MSLB TRACG analysis is an evaluation the provided a justification for continue operation for Dresden Units 2/3 and Quad Cities Units 1 and 2. The acceptance criteria for this analysis is that during a worst case accident (i.e., main steam line break (MSLB)) the shroud and attached channel guides will not lift above the top of the fuel channels, even when the shroud separates. To perform this analysis several programs are used to provide input to TRACG. The TRACG simulated reactor pressure vessel pressure gradients are use as inputs to a spread sheet calculation and subsequently in a computer program, SHRD-LIFT2, to calculate the vertical lift distance. This dynamic lift distance can not exceed the vertical distance between the bottom of the channel guides and the top of the fuel channels.
The Cycle 14 Quad Cities Unit 1 station reactor vessel and core geometries were used and were assumed to bound Dresden Units 2 and 3, and Quad Cities Unit 2. PANACEA, ISCOR, and ODYN-SS results were used as input to a computer program, ATRAC, which produced an input deck for TRACG. Values not provided by the three programs were provided by the analyst. Once the TRACG input deck was prepared, TRACG was used to simulate the MSLB. The output from TRACG was used in a spread sheet and in SHRD-LIFT2 to predict the vertical lift of the shroud.
The TRACG Qualification documented in NEDE-32177P, Rev. 1, June 1993 was reviewed. In Section 3.1.5, the PSTF level swell tests were simulated using TRACG. This simulation represented a steam line break. Water level and break flow appeared to match the test data. It was concluded from this review that TRACG was validated for the MSLB analysis.
In reviewing the DRF L12-00817, the following deficiencies were found relating to
CAR G-97-120-01:
"MSLB TRACG analysis": Many of the pages of the DRF did not have page numbers
or the DRF identified. This should be corrected for all sections of this DRF which apply.
The output files that were used for ATRAC could not be determined from the
documentation.
"ISCOR calculation of Quad Cities Cycle 14": This calculation was represented by
computer input and computer output. The output used for input to ATRAC was difficult to follow from the lack of organized documentation.
"PANACEA Calculation of Quad Cities": This calculation was represented by
computer input and computer output. The output used for input to ATRAC was difficult to follow from the lack of organized documentation.
"ODYN-SS Calculation of Quad Cities": This calculation was represented by some
minor calculations and a computer input and computer output. The output was used for input to ATRAC was difficult to follow from the lack of organized documentation.
ATRAC Calculation of Quad Cities, this calculation used input from ISCOR, PANACEA,
OPL-3, and ODYN-SS to develop input to TRACG. ATRAC identified values that were needed to complete the TRACG input. These values were developed as part of the DRF. The output used for input to ATRAC was difficult to follow from the lack of organized documentation.
(See CAR G-97-120-01)
In reviewing the MSLB TRACG analysis, DRF L12-00817, the following deficiencies were found relating to CAR G-97-120-3:
An OPL-3 from Quad Cities Unit 1 was used to bound the Quad Cities Unit 2 and Dresden Units 2 &3. The basis for Quad Cities Unit 1 OPL-3 values bounding the Quad Cities Unit 2 and Dresden Units 2 & 3 was that Quad Cities Unit 1 has been analyzed for 108 % core flow and Dresden has not. Therefore the Quad Cities Unit 1 conditions are expected to bound conditions of Dresden. However, If Dresden performed a new design basis calculation to increase core flow to 108%, there does not appear to be a GE process or control to trigger a reassessment of the MSLB TRACG Analysis. This is a Lack of Control of Design Input. This calculation was performed for Quad Cities 1 & 2 and Dresden 2 & 3. This DRF did not represent LaSalle.
Data was taken from a data base identified as LaSalle FDS.CYCLE.CEO and was used as input to the MSLB analysis for Quad Cities and Dresden. Apparently, the FDS.CYCLE.CEO is a GE controlled data base. However if data in FDS.CYCLE.CEO, that was used in the MSLB analysis, is changed, there is no mechanism in place to ensure that the potential impact on the MSLB DRF is evaluated. This is a Lack of Control of Design Input.
ISCOR calculation for Quad Cities Cycle 14, this calculation was represented by computer input and computer output. The output used for input to ATRAC was not clearly organized and was difficult to follow. References were not given which made the inputs not traceable.
PANACEA calculation for Quad Cities Cycle 14, this calculation was represented by computer input and computer output. The output used for input to ATRAC was not clearly organized and was difficult to follow. References were not given which made the inputs not traceable. Cycle 13 input was used instead of Cycle 14. No comparison or justification for use of Cycle 13 data for applicability to a cycle 14 analysis. The validity of this design input was not demonstrated.
ODYN-SS calculation for Quad Cities, this calculation was represented by some minor calculations, computer input and computer output. The output used for input to ATRAC was not clearly organized and was difficult to follow. References were not given which made the inputs not traceable.
ATRAC calculation for Quad Cities, this calculation used input from ISCOR, PANACEA, OPL-3, and ODYN-SS to develop input to TRACG. ATRAC identified values that were needed to complete the TRACG input. These values were developed as part of the DRF. Some of the values did not have adequate references, e.g., separator pitch. Traceable references were not given. The output used for input to ATRAC was not clearly organized and was difficult to follow. References were not given which made the inputs not traceable.
TRACG Calculation of Quad Cities, the decay power used to perform the TRACG calculation was not referenced. References were not given which made the inputs not traceable.
(See CAR G-97-120-03)
In reviewing the MSLB TRACG analysis, DRF L12-00817, the following additional deficiencies were found:
The lift calculation is a key aspect of the calculation. The computer program, SHRD-LIFT2, was used to determine the lift of the shroud. The results of this calculation was provided in the final report to ComEd. There is no documentation of the computer program. There is no documented verification or validation of the computer program. (See CAR G-97-120-07)
A Sargent and Lundy engineer provided design information and input to General Electric. A GE engineer indicated that ComEd told him, verbally, that the Sargent and Lundy engineer represents ComEd. In the input section, design input was sent from Sargent and Lundy directly to General Electric without design review by ComEd. (See CAR G-97-120-08)
19. WATER LEVEL INSTRUMENTATION SUPPORT-DRF B21-0537
This DRF contained many calculations which were used to determine the acceptability of the back fill of cold water from the control rod fill pumps into the hot condensing pots which are used to determine water level in the reactor vessel. The calculations consisted of three parts. The thermal/hydraulic, stress and set point bias calculations. The acceptance criteria is to satisfy the ASME stress allowable, due to the flow of the cold water into the condensing pot and down the steam leg into the reactor vessel. These analyses were performed for Dresden, Quad Cities and LaSalle.
In reviewing the DRF B21-0537, the following deficiencies were found relating to
CAR G-97-120-01:
Water Level Instrumentation Support- "Calculation RVWLLS Condensing Chamber,":
Could not read calculation and drawings.
"Mixed Mean Model Spread Sheet Usage,": Calculation document illegible.
"Calculation of Puddle Depth in the CC at LaSalle,": Calculation document illegible.
"Calculation Heat Transfer Coefficient Estimate,": Calculation document illegible.
"Calculation of Flow Area Used in the 1D Stratification,": Calculation document illegible.
"Calculation of Condensing Chamber Data Flow Split Calculation,": Calculation
document illegible.
"Data Used in EXCEL Spread Sheet (Mixed Mean Temperature),": Calculation
document illegible.
"Steam Leg Depth Calculation,": Calculation document illegible.
(See CAR G-97-120-01)
In reviewing the DRF B21-0537, the following deficiencies were found relating to
CAR G-97-120-02:
Water of Cond. Pot section, the sign off sheet was signed by preparer and reviewer,
but not approved. The reviewer had comments, but resolution of the comments were not documented and comments were not resolved. There was an inadequate completion of required design review documentation.
RVWLLS Cond. Chamber section, the sign off sheet was missing. A sheet signed by
the preparer, reviewer, and approver was either never completed or destroyed during microfiching.
This is inadequate design review documentation.
Mixed Mean Model Spreadsheet section, the sign off sheet was missing. A preparer
was identified on the calculation sheets but not a reviewer. A sheet signed by the preparer, reviewer, and approver was either never completed or destroyed during microfiching. This is inadequate design review documentation.
LS Puddle Depth in the CC at LaSalle section, the sign off sheet was missing. A
preparer was identified on the calculation sheets but not a reviewer. A sheet signed by the preparer,
reviewer, and approver was either never completed or destroyed during microfiching. This is
inadequate design review documentation.
H/T Coef. Estimate section, the sign off sheet was missing. A preparer was identified
on the calculation sheets and a reviewer. A sheet signed by the preparer, reviewer, and approver was either never completed or destroyed during microfiching. This is inadequate design review
documentation.
Flow Area, 1D Stratification section, the sign off sheet was missing. A preparer was
identified on the calculation sheets and a reviewer. A sheet signed by the preparer, reviewer, and
approver was either never completed or destroyed during microfiching. This is inadequate design
review documentation.
Cond. Chamber Flow Split section, the sign off sheet was missing. A preparer was identified on the calculation sheets and a reviewer. A sheet signed by the preparer, reviewer, and approver was either never completed or destroyed during microfiching. This is inadequate design review documentation.
Data used in EXCEL Spreadsheet section, the sign off sheet was missing. A preparer
was identified on the calculation sheets and a reviewer. A sheet signed by the preparer, reviewer, and approver was either never completed or destroyed during microfiching. This is inadequate design review documentation.
Steam Leg Depth Calc section, the sign off sheet was missing. A preparer was
identified on the calculation sheets and a reviewer. A sheet signed by the preparer, reviewer, and
approver was either never completed or destroyed during microfiching. This is inadequate design
review documentation.
H/T Coef. DR & QC section, the sign off sheet was missing. A preparer was identified
on the calculation sheets but not a reviewer. A sheet signed by the preparer, reviewer, and approver
was either never completed or destroyed during microfiching. This is inadequate design review
documentation.
Rx Water & Instr. Nozzle Data section, the sign off sheet was missing. A preparer was
identified on the calculation sheets and a reviewer. A sheet signed by the preparer, reviewer, and
approver was either never completed or destroyed during microfiching. This is inadequate design
review documentation.
Length of 2" pipe for QC section, the sign off sheet was missing. A preparer was
identified on the calculation sheets but not a reviewer. A sheet signed by the preparer, reviewer, and approver was either never completed or destroyed during microfiching. This is inadequate design review documentation.
2nd Data used in EXCEL Spreadsheet section, the sign off sheet was missing. A
preparer was identified on the calculation sheets and a reviewer. A sheet signed by the preparer,
reviewer, and approver was either never completed or destroyed during microfiching. This is
inadequate design review documentation.
(See CAR G-97-120-02)
In reviewing the DRF B21-0537, the following deficiencies were found relating to
CAR G-97-120-03:
Dresden Backfill Section, GENE-637-031-1093, dated October 1993, the calculations for the cold liquid flow into the condensing pot. design inputs of 15 lb/hr and 19 lb/hr (found on page 3 of the report) did not have any reference which made the inputs not traceable. This brings the validity of these design inputs into question.
In Report "LaSalle Unit 2 Reactor Vessel Water Level Instrumentation System Backfill Report", GENE # 637-027-0993, many of the design inputs have no references and therefore the basis can not be established. An example of this is on page 10 & 11 of the report. Other examples were found on pages 28, 29, 30, 31, 32, 33, 34, 35 and 36. The lack of references make the inputs not traceable. This brings the validity of these design inputs into question.
"Reactor Water Level Backfill", an Engineering Services Verification Cover Sheet (Ref. EOP 42-6.00 and EOP 25-6.00), related to the " Revised Heat Transfer Coefficients" was prepared on 11/8/93 by Joe Darr and approved by Hank Phefferlen on 11/21/95, but the report included and the DRF were approved 9/9/93. It appears that design analyses were performed after the DRF was approved. It was not clear from the DRF if the revised heat transfer calculation was used as a design input for a 1993 report or for a 1995 report. The heat transfer coefficient design input was changed without proper controls or references.
Report # GENE-637-031-1093, the RPV level instrumentation bias should be evaluated against the setpoint methodology program to ensure that the set point basis was addressed. No evidence or references could be found that this evaluation was performed. The lack of references make the inputs not traceable. This brings the validity of these design inputs into question.
Water of Cond. Pot calculation, the lack of a response to the reviewers comments on the design verification brings the validity of these design inputs into question.
RVWLLS Cond. Chamber calculation, the lack of legibility and design verification brings the validity of these design inputs into question.
Mixed Mean Model Spreadsheet calculation, the lack of legibility and design verification brings the validity of these design inputs into question.
LS Puddle Depth in the CC at LaSalle calculation, the lack of legibility and design verification brings the validity of these design inputs into question.
H/T Coef. Estimate calculation, the lack of legibility and design verification brings the validity of these design inputs into question.
Flow Area, 1D Stratification calculation, the lack of legibility and design verification brings the validity of these design inputs into question.
Cond. Chamber Flow Split calculation, the lack of legibility and design verification brings the validity of these design inputs into question.
Data used in EXCEL Spreadsheet calculation, the spreadsheet itself was not provided in the DRF. The lack of legibility and design verification brings the validity of these design inputs into question.
Steam Leg Depth calculation, the lack of legibility and design verification brings the validity of these design inputs into question.
H/T Coefficient "h" for DR & QC calculation, the lack of references and design verification brings the validity of these design inputs into question.
Rx Water & Instr. Nozzle Data calculation, the lack of design verification brings the validity of these design inputs into question.
Length of 2" pipe for QC calculation, the lack of design verification brings the validity of these design inputs into question.
2nd Data used in EXCEL Spreadsheet (Mixed Mean Temperature) calculation, the lack of legibility and design verification brings the validity of these design inputs into question
(See CAR G-97-120-03)
In reviewing the DRF B21-0537, the following deficiencies were found relating to
CAR G-97-120-05:
ComEd Engineering personnel prepared and performed independent verification of calculations under GENE QA Program without being indoctrinated and trained. Furthermore, GENE violated its program by not using its own employees. The following calculations were affected:
Water of Cond. Pot section.
RVWLLS Cond. Chamber section.
Mixed Mean Model Spreadsheet section.
LS Puddle Depth in the CC at LaSalle section.
H/T Coef. Estimate section.
Flow Area, 1D Stratification section.
Cond. Chamber Flow Split section
Data used in EXCEL Spreadsheet section.
Steam Leg Depth Calc section.
H/T Coef. DR & QC section.
Rx Water & Instr. Nozzle Data section.
Length of 2" pipe for QC section.
2nd Data used in EXCEL Spreadsheet section.
(See CAR G-97-120-05)
In reviewing the DRF B21-0537, the following item was noted as an Unresolved Item:
This DRF was approved on 9/8/93. The sign off sheet for this design document changing the heat transfer coefficient was approved on 11/21/95. Why wasn't the design document revised for this change, which constitutes a need for revision? Were the preparer and design verifier of this design document aware of this change to reevaluate the impact? (See CAR G-97-120-12 Item A)
Corrective Action:
GENE Engineering Operating Procedure No. EOP 75-3.00 revision 5, dated 7/30/97 addresses self assessments, corrective actions and audits. In the corrective action area, the Problem Evaluation Request (PER’s) form is utilized as a process of identifying a condition which could be adverse to quality. The PER process is identified to assure that conditions adverse to quality, such as potential causes of nonconforming product, failures, malfunctions, deficiencies, deviations, and other quality conditions. There are no restrictions as to who can identify and generate a PER.
PER’s are reviewed for validity and to determine the need for a root cause analysis, committed corrective action, and committed preventive action. Each of the PER’s receives a quality review. Adverse conditions are required to be communicated to the client. A reportability review and notification is intended to be performed per P&P 70-42. A review of four recently issued PER’s during the course of this audit revealed that PER’s are generated in accordance with approved procedures and that they are required to receive the appropriate review by the Engineering Manager, Quality Assurance and the assigned individual. Each of the PER’s reviewed were not dispositioned as yet since the PER process was started on July 31, 1997.
PER No. TS-97-004 was generated during this audit by GENE’s Regulatory Services Project Manager to document the deficiency identified by this audit regarding ComEd personnel performing design analysis on the CECo water level modification analysis project under the GE QA Program (CAR No. G-97-120-05). This was the only PER issued by GENE during this audit. The GENE QA Manager indicated that once GENE receives the audit findings from ComEd they will be evaluated for PER status
Internal Audits:
GENE was found to have an approved internal 1997 scheduled audit plan for Customer Services Asia & Europe, GENE Sourcing and Support, Information Management Systems, Nuclear plant projects, and Nuclear Services Department as administered by Nuclear Services Quality (NSQ). NSQ gets input from a particular business unit, selects specific jobs, develops a plan, schedule and distributes the information to the responsible departments. Checklists are then derived and generated for the specific activity being audited.
The information provided by the GENE QA Organization revealed that internal audits did not perform a technical review of design activities. The audit team after carefully reviewing several internal GENE audits, determined that no evidence exists which demonstrates that QA reviews the programmatic aspects of the design calculation portion of the DRF. After the exit meeting G.E. faxed some additional samples of audits to demonstrate a programmatic review of the design calculation portion of the DRF. However, these examples were found lacking to support a review of the design portion of the DRF. Therefore, the audit team assessed that the GENE's internal audits are ineffective in independently overviewing the design analysis area.
This area was found deficient and identified as a Level II Finding CAR-G-97-120-06
Indoctrination/Training:
Policies & Procedures NEDE-31746 Procedure No. 70-30 issued 8/94 has established the minimum personnel proficiency requirements to be implemented by each manager of employees performing activities affecting the quality of GENE products. Qualification for technical positions are documented to include minimum education, experience and/or special technical requirements. Employees responsible for adherence to Code or regulatory requirements shall maintain their knowledge of current provisions of such Codes, rules, and regulations.
Each person, prior to assignment of work activity affecting quality of products, shall be indoctrinated or instructed in the applicable quality system procedures. Indoctrination and training shall be attained and maintained. Contrary to the above procedural requirements, several ComEd Engineers were found to have performed and reviewed design analysis calculations under the GENE QA Program. In addition to not being employed by G.E. they were not indoctrinated and trained to GENE procedures.
This area was found deficient and identified as a Level II Finding CAR-G-97-120-05
EOP 40-9.00 rev. 10 provides responsibilities and procedures requirements to meet the ASME Boiler & Pressure Vessel Code (BPV) requirements for Certification of Design Specification, Design Drawings and Reports, Load Capacity Data Sheets, Overpressure Protection Reports, and Construction Specifications. Appendix A of the subject procedure indicates that Registered Professional Engineers must meet the requirements of Code and ASME/ANSI N626.3-1993 in order to certify the above stated documents. Interview with the GENE QA and Engineering Managers revealed that no such certification activities has been performed in the past three years. The qualification of inspection personnel, auditors, NDE personnel was not part of the scope of this audit.
There were no ASME Class 1 pressure boundary activities performed by GENE for ComEd for the past three years.
Attachments
Attachment 1 - Entrance/Exit Meeting Attendance
Attachment 2 - Audit Team
Attachment 2 - Personnel Contacted During the Audit
Attachment 1
Entrance / Exit Meeting Attendance
Entrance Meeting (8/18/97)
Name Title Organization
Oscar Shirani Audit Team Leader ComEd
Yakub A. Patel Technical Specialist ComEd
Albert Lie-Mien Sheng Technical Specialist EMS
YuHua Chen Technical Specialist EMS
George B. Strambach Regulatory Services, PM GENE
Dave Grim Regulatory Engr./Tech. Account Interface GENE
Robert J. Nicholls Manager-Nuclear Services Quality GENE
Shyam S. Dua Plant Analysis Services Manager GENE
Bradley J. Erbes Engineering Resource Manager GENE
Joe Quirk Industry Programs GENE
Noel Shirley Principal Engineer GENE
Exit Meeting (8/22/97)
Name Title Organization
Oscar Shirani Audit Team Leader ComEd
Yakub A. Patel Technical Specialist ComEd
YuHua Chen Technical Specialist EMS
Joe Miller Techncial Specialist EDA
John Freeman Lead BWR Safety Analysis ComEd
Lie-Mien (Albert) Sheng Technical Specialist EMS
George B. Strambach Regulatory Services, PM GENE
Shyam S. Dua Plant Analysis Sevices Manager GENE
Robert J. Nicholls Manager-Nuclear Services Quality GENE
Saul Mintz Senior Engineer GENE
Carl Young Principal Engineer GENE
Har Mehta Principal Engineer GENE
Cherk Chu Principal Engineer GENE
Hwang Choe Principal Engineer GENE
Gerald Hayes Manager, Engineering GENE
D. R. Helwig General Manager Nuclear Services GENE
P. T. Tran Engineer Leader GENE
N. E. Barclay Manager Audits GENE
Noel Shirley Principal Engineer GENE
Gary Plotycia Nuclear Account Executive ComEd
Attachment 2
Audit Team
Audit Team
Name Title Organization
O. B. Shirani Audit Team Leader ComEd
Y. A. Patel Technical specialist ComEd
N. Chen Technical specialist EMS
A. Sheng Technical Specialist EMS
J. Freeman Technical Specialist ComEd
J. Miller Technical Specialist EDA
Personnel Contacted During Audit
Name Title Organization
H. S. Mehta Principal Engineer GENE
P. K. Shah Engineer GENE
C. Chu Engineer GENE
M. Romero Engineer GENE
George B. Strambach Regulatory Services, PM GENE
Shyam S. Dua Plant Analysis Sevices Manager GENE
Robert J. Nicholls Manager-Nuclear Services Quality GENE
Har Mehta Principal Engineer GENE
Cherk Chu Principal Engineer GENE
Hwang Choe Principal Engineer GENE
N. E. Barclay Manager Audits GENE
Noel Shirley Principal Engineer GENE